Title: Airport Terminal Elevated Roadway System and Pedestrian Tunnels

Title

Airport Terminal Elevated Roadway System and Pedestrian Tunnels

 

Action

Action:

A.                     Approve contract amendment #3 for $740,000 with HNTB of North Carolina for construction administration and inspection services, and

 

B.                     Approve contract amendment #1 for $192,500 with Summit Engineering, Laboratory, & Test, P.C. for quality testing.

 

Body

Staff Resource(s):

Brent Cagle, Aviation

Jack Christine, Aviation

 

Explanation

Action A

§                     On November 8, 2010, City Council approved a design contract to HNTB of North Carolina, P.C. (HNTB) in the amount of $1,292,280 for the terminal elevated roadway system.

§                     On September 10, 2012, City Council approved contract amendment #1 in the amount of $362,081 to HNTB for additional design services.

§                     On August 24, 2015, City Council approved a construction contract for the Terminal Elevated Roadway System project, and also approved contract amendment #2 with HNTB in the amount of 1,617,669, for the construction administration of the project.

§                     The construction is projected to be complete September 2019, and contract amendment #3 will ensure continuity of construction administration, scheduling, project controls, and field inspections.

§                     The new total of the contract, including this amendment, is $4,012,030.

§                     This activity is occurring on airport property, Council District 3.

Action B

§                     On August 24, 2015, City Council approved a contract with Summit Engineering, Laboratory, & Testing, P.C. in the amount of $1,971,800 for quality assurance and special inspections.

§                     The construction is projected to be complete September 2019, and this amendment will ensure continuity of quality assurance testing, bridge inspection, caisson inspection, and special inspections.

§                     The new total of the contract, including this amendment, is $2,164,300.

 

Charlotte Business INClusion

Action A

All additional work involved in this amendment will be performed by HNTB of North Carolina and their existing subcontractor (Part D: Section 6 of the Charlotte Business INClusion Policy).

HNTB of North Carolina has committed 2.70% ($20,000) of the total contract amendment amount to the following certified firm:

§                     McFarland Building Group, LLC (SBE, MBE) ($20,000) (progress meetings and document control)

 

Action B

All additional work involved in this amendment will be performed by Summit Engineering, Laboratory, & Testing, P.C. and their existing subcontractor (Part D: Section 6 of the Charlotte Business INClusion Policy).

Summit Engineering, Laboratory, & Testing, P.C. has committed 10.00% ($19,250) of the total contract amendment amount to the following certified firm:

§                     On-Spec Engineering (SBE) ($19,250) (materials testing)

 

Fiscal Note

Funding:  Aviation Community Investment Plan