Title: Charlotte-Mecklenburg Police Department Hangar Relocation Progressive Design-Build Project
Attachments: 1. Map - CMPD Hangar Relocation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Charlotte-Mecklenburg Police Department Hangar Relocation Progressive Design-Build Project

 

Action

Action                     

Approve a contract in the amount of $1,621,665 with J. E. Dunn Construction Company for Design-Build initial design services for Charlotte-Mecklenburg Police Department Hangar Relocation Progressive Design-Build project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Casey Mashburn, General Services

Mary Herington, General Services

 

Explanation

§                     In October 2024, the city acquired and successfully rezoned an 11.79-acre site on the north side of Billy Graham Parkway, located in Council District 3, to support the relocation of the Charlotte-Mecklenburg Police Department (CMPD) Aviation Division.

-                     The new site will replace the current CMPD Helicopter Hangar, located on Charlotte Douglas International Airport property that conflicts with ongoing and planned airfield development.

-                     This project provides CMPD’s Aviation Unit with a facility that supports their continued operations and provisions for future growth.

§                     On February 11, 2025, the city issued a Request for Qualifications (RFQ); nine responses were received.

§                     J. E. Dunn Construction Company is the best qualified firm to meet the city’s needs on the basis of demonstrated competence and qualification of professional services in response to the RFQ requirements.

§                     Progressive Design-Build projects consist of two phases; the Design Phase delivers the project design, and Construction Phase will provide a guaranteed maximum price to construct the project.

§                     A future Council Action for an amendment will be requested for the construction phase.

 

Charlotte Business INClusion

The city negotiates contract participation for Design-Build contracts after the firm is selected, and scopes of work are defined for design and construction services. J. E. Dunn Construction Company has committed ($512,400) or approximately 31.60% of the contract for design services to the following certified firm(s):

§                     AME Consulting Engineers, PC (SBE) ($155,000) (MEP design)

§                     Avcon, Inc. (MBE) ($285,000) (civil engineering, FAA design)

§                     Stewart Engineering Inc. (MBE) ($72,400) (structural design)

 

 Fiscal Note

Funding: General Capital Investment Plan

 

Attachments

Attachment(s)

Map