File #: 15-2252    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 12/30/2015 In control: City Council Business Meeting
On agenda: 1/25/2016 Final action: 1/25/2016
Title: Bobby Lane and Nancy Drive Storm Drainage Improvements
Attachments: 1. Location Map - Bobby Lane and Nancy Drive Storm Drainage Improvements

Title

Bobby Lane and Nancy Drive Storm Drainage Improvements

 

Action

Action:                       

Award a contract in the amount of $943,886.08 to the lowest responsive bidder Sealand Contractors Corp. for the Bobby Lane and Nancy Drive Storm Drainage Improvements project.

 

Body

Staff Resource(s):

Stewart Edwards, Engineering & Property Management

 

Explanation

§                     The project involves installing approximately 1,160 feet of new storm drainage and replacing associated utilities along Bobby Lane and Nancy Drive. This project is in Council District 5 off of Craig Avenue and is surrounded by Wendover Road, Monroe Road, Sharon Amity Road, and Randolph Road.

§                     The work will include:

-                     Storm drainage,

-                     Sanitary sewer,

-                     Water line,

-                     Sidewalk,

-                     Curb and gutter,

-                     Driveways, and

-                     Asphalt pavement replacement.

§                     On November 20, 2015, the City issued an Invitation to Bid for the Bobby Lane and Nancy Drive Storm Drainage Improvement project; six bids were received from interested service providers.

§                     Sealand Contractors Corp. was selected as the lowest responsive, responsible bidder.

§                     Construction is expected to be completed by the end of third quarter 2016.

 

Charlotte Business INClusion

Established SBE Goal: 14%

Committed SBE Goal: 14.00%

Sealand Contractors Corp. met the established SBE subcontracting goal, and has committed 14.00% ($132,145) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

                     Darnell Jones Trucking, Inc. (SBE, MBE) ($67,567) (hauling)

                     On Time Construction, Inc. (SBE, MBE) ($62,610) (concrete/masonry)

                     A1 Precision Fence Company (SBE) ($1,968) (fence installation)

 

Established MBE Goal: 6%

Committed MBE Goal: 13.79%

Sealand Contractors Corp. exceeded the established MBE subcontracting goal, and has committed 13.79% ($130,177) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

                     Darnell Jones Trucking, Inc. (SBE, MBE) ($67,567) (hauling)

                     On Time Construction, Inc. (SBE, MBE) ($62,610) (concrete/masonry)

 

Fiscal Note

Funding:  Storm Water Community Investment Plan

 

Attachments

Attachment

Map