File #: 15-15424    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 3/16/2021 In control: City Council Business Meeting
On agenda: 5/10/2021 Final action:
Title: Dairy and Derita Branch Tributaries Sanitary Sewer Construction
Attachments: 1. Dairy Branch Tributary - Sedgefield Park Segment Sanitary Sewer Map, 2. Derita Branch Tributary Trunk Sanitary Sewer Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Dairy and Derita Branch Tributaries Sanitary Sewer Construction

 

Action

Action                     

Approve a guaranteed maximum price of $17,977,441 to B.R.S., Inc. for Design-Build construction services for the Dairy Branch Tributary - Sedgefield Park and Derita Branch Tributary Trunk Sanitary Sewer projects.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     B.R.S., Inc. has developed a guaranteed maximum price (GMP) for construction of the Dairy Branch Tributary - Sedgefield Park segment and a portion of the Derita Branch Tributary Trunk Sanitary Sewer projects.

-                     The Dairy Branch Tributary - Sedgefield Park segment will upsize the existing sanitary sewer line starting at McDonald Avenue, through Sedgefield Park, and will end at South Boulevard (Council District 1).

-                     The Derita Branch Tributary Trunk Sanitary Sewer project will upsize the existing sanitary sewer line, which will require tunnel crossings of North Tryon Street and Interstate 85 (Council Districts 1 and 4).

§                     On December 12, 2018, City Council approved a contract with B.R.S., Inc. for Design-Build design services for the Dairy and Derita Branch Tributaries projects.

§                     On February 24, 2020, City Council approved a GMP for the Dairy Branch Tributary - Freedom Park segment, the first segment of the Dairy Branch Tributary project.

§                     The Dairy Branch Tributary - Sedgefield Park segment is anticipated to be complete by third quarter 2022. The Derita Branch Tributary Trunk Sanitary Sewer project is expected to be complete by fourth quarter 2023.

§                     City Council will receive future requests for approval of remaining project GMPs.

 

Charlotte Business INClusion

The city negotiates participation for Design-Build contracts after the firm is selected and scopes of work are defined for design and construction services (Part G: Section 2.7 of the Charlotte Business INClusion Policy). B.R.S., Inc. has committed $1,499,515 or approximately 8.34% of the total contract for construction services to the following certified firms:

§                     Turn-Key Tunneling, Inc. (WBE) ($469,920) (sewer tunneling, boring)

§                     Trull Contracting, Inc. (WBE, SBE) ($253,600) (paving, sidewalks, curb, and gutter)

§                     Sanders Constructors, Inc. (SBE) ($189,000) (clearing, grubbing, and tree removal)

§                     CES Group Engineers, LLP (WBE, SBE) ($128,875) (surveying, staking, layout, and as-built survey)

§                     GDC, Inc. (MBE, SBE) ($86,000) (traffic control)

§                     Luvall Asphalt Services, Inc. (MBE, SBE) ($85,000) (asphalt replacement, milling, and overlay)

§                     MTS Trucking Inc. (MBE, SBE) ($79,000) (hauling)

§                     Hinde Engineering, Inc. (SBE) ($38,970) (utility coordination)

§                     Martin Landscaping Co. Inc. (MBE, SBE) ($29,100) (matting, permanent seeding, and mulching)

§                     Pipe Pros, LLC (SBE) ($29,000) (cctv)

§                     Maybury Fencing, Inc. (WBE, SBE) ($25,000) (fencing installation and rental)

§                     Diamond Trucking of NC, Inc. (MBE, SBE) ($20,000) (hauling)

§                     Gavel & Dorn Engineering, PLLC (SBE) ($20,000) (sewer modeling)

§                     CriTek Engineering Group, P.C. (MBE, SBE) ($15,000) (erosion control design)

§                     Mid-Atlantic Erosion Control, Inc. (SBE) ($12,000) (silt fence and erosion control)

§                     JB Long Photography (SBE) ($9,450) (preconstruction photography)

§                     All Things Professional (SBE) ($6,600) (field office cleaning)

§                     Soggy Bottom Erosion Control (SBE) ($3,000) (silt fence)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 

Attachments

Attachment(s)

Dairy Branch Tributary - Sedgefield Park Segment Sanitary Sewer Map
Derita Branch Tributary Trunk Sanitary Sewer Map