Skip to main content
City of Charlotte Banner
File #: 15-2108    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 12/15/2015 In control: City Council Business Meeting
On agenda: 1/25/2016 Final action: 1/25/2016
Title: LYNX Blue Line Extension Civil B/C Change Order

Title

LYNX Blue Line Extension Civil B/C Change Order                     

 

Action

Action:

Approve a change order in the amount of $4,500,000 to the LYNX Blue Line Extension Civil B/C Construction contract with The Lane Construction Corporation.

 

Body

Staff Resource(s):

John Lewis, CATS

Jeb Blackwell, Engineering

Danny Rogers, CATS

 

Explanation

§                     On April 14, 2014, the City Council awarded the Blue Line Extension (BLE) Civil construction contract for segment B/C, from Old Concord Road to the end of line at UNC Charlotte, to The Lane Construction Corporation in the amount of $119,051,742.33.

§                     On January 26, 2015, City Council approved a contract amendment in the amount of $21,700,000 to settle delay claims related to utility relocations and to accelerate the work to recover the contract schedule.

§                     The change order will transfer $4.5 million from the overall BLE project contingency to the Civil B/C contract with The Lane Construction Corporation.  These funds will be used to further accelerate the project schedule and to complete the following additional work items: 

-                     Upgrade the fencing from welded wire to galvanized steel picket along North Tryon Street to improve the visual quality of the corridor;

-                     Add luminaire arms on signal poles;

-                     Modify intersection design to improve pedestrian safety;

-                     Design and quantity revisions based on field conditions and utility conflicts;

-                     Add an additional payment and incentive to further accelerate Segments B and C.  The earlier completion will allow the Track and Systems contractor to proceed with a more efficient sequence of work.

§                     The costs associated with this amendment are within the current project budget from existing project contingency.

§                     The new total value of the contract with The Lane Construction Corporation is $145,251,742.33.

 

Disadvantaged Business Enterprise (DBE)

Any additional contract scope authorized by this change order will be held to the original contract DBE goal of 20%.

 

Fiscal Note

Funding:  CATS Community Investment Plan