Legislation Details

File #: 15-25775    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 2/27/2026 In control: City Council Business Meeting
On agenda: 5/11/2026 Final action:
Title: Water Transmission Main Improvements and Repair
Attachments: 1. Map - Water Transmission Main Improvements and Repair, 2. Map - Iron District Transmission Main, 3. Map - Old Statesville Rd Transmission Main, 4. Map - Old Statesville Rd Valve Replacement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Water Transmission Main Improvements and Repair

 

Action

Action                     

Approve a contract amendment for $4,317,453 to State Utility Contractors, Inc. for additional Design-Build design and construction services for the Water Transmission Improvements and Repairs Project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Chuck Bliss, Charlotte Water

 

Explanation

§                     On June 8, 2020, following a competitive solicitation process, City Council approved a contract with State Utility Contractors, Inc. in the amount of $1,923,793 for Design-Build design services for Water Transmission Main Improvements and Repairs.

§                     This contract amendment includes:

-                     Design of a water transmission main in the Iron District along Cedar Street in Council District 2,

-                     Design for replacing a water transmission main in Old Statesville Road from Gibbon Road to Pete Brown Road in Council District 2, and

-                     Construction costs for replacing an existing valve necessary for distribution system on Old Statesville Road near Independence Hill Road adjacent to Council District 4.

§                     Requests for the approval of additional guaranteed maximum prices for construction of various project segments will be presented to City Council in the future.

§                     The project is anticipated to be complete by the first quarter of 2027.

 

Charlotte Business INClusion

The city negotiates contract participation for Design-Build contracts after scopes of work are defined for construction services. State Utility Contractors, Inc. has committed ($136,125) or 3.15% of the contract amendment for design and construction services to the following certified firm(s):

§                     Froehling & Robertson, Inc. (MBE) ($14,225) (geotechnical drilling and investigations)

§                     JM Custom Construction, LLC (WBE, SBE) ($4,200) (concrete) 

§                     Lawrence Associates PA (SBE) ($3,500) (surveying)

§                     Trull Contracting, LLC (SBE) ($114,200) (asphalt repair and traffic markings)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 

Attachments

Attachment(s)

Maps