Title: Construct University Research Park Sidewalk
Attachments: 1. Map - Construct University Research Park Sidewalk.pdf

Title

Construct University Research Park Sidewalk

 

Action

Action:                       

Approve a contract in the amount of $1,156,273.25 to the lowest responsive bidder Sealand Contractors Corp. for the University Research Park Sidewalk project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Jennifer Smith, General Services

 

Explanation

§                     The University Research Park Sidewalk project will improve pedestrian safety and mobility around University Research Park in Council District 4.

§                     The contract includes the construction of concrete sidewalk and shared-use paths in three locations:

−                     Medical Plaza Drive between Harris Boulevard and Mallard Creek Road,

−                     The intersection of David Taylor Drive and Claude Freeman Drive to the intersection of Governor Hunt Road and David Taylor Drive, and

−                     Claude Freeman Drive from the intersection of David Taylor Drive and Claude Freeman Drive to the first business entrance at the right side of Claude Freeman Drive.

§                     The improvements include but are not limited to curb ramps, retaining wall, storm drainage system, and water line relocation.

§                     On July 3, 2023, the city issued an Invitation to Bid; five bids were received.

§                     Sealand Contractors Corp. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by third quarter 2024.

 

Charlotte Business INClusion

Established MBE Goal: 8.00%

Committed MBE Goal: 8.00%

 

Sealand Contractors Corp. met the established contract goal and has committed 8.00%

($92,510) of the total contract amount to the following certified firm(s):

§                     Streeter Trucking Company, Inc. (MBE, SBE) ($92,510) (hauling)

 

Established SBE Goal: 16.00%

Committed SBE Goal: 16.00%

 

Sealand Contractors Corp. met the established contract goal and has committed 16.00%

($185,040) of the total contract amount to the following certified firm(s):

§                     On Time Construction, Inc. (WBE, SBE) ($80,700) (concrete, masonry)

§                     Whitesell Trucking, Inc. (SBE) ($68,865) (clearing, grubbing)

§                     AMP Utility Distribution Services, LLC (WBE, SBE) ($19,240) (utility material)

§                     Cochise Trucking (SBE) ($6,500) (hauling)

§                     Pentacle Inc (WBE, SBE) ($3,040) (hauling)

§                     Erosion Defence LLC (SBE) ($6,695) (erosion control)

 

Fiscal Note

Funding:  General Capital Investment Plan

 

Attachments

Attachment(s)

Map