Title: Beaverdam Creek Trunk Sewer Phase 2
Attachments: 1. Map - Beaverdam Creek Trunk Sewer Phase 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Beaverdam Creek Trunk Sewer Phase 2

 

Action

Action                     

Approve a contract in the amount of $1,295,019 to the lowest responsive bidder State Utility Contractors for the Beaverdam Creek Trunk Sewer Phase 2 project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Chuck Bliss, Charlotte Water

 

Explanation

§                     This contract will provide for the installation of a sanitary sewer pipeline to serve customers located in the Beaverdam Creek Basin in Charlotte (adjacent to Council District 3).

§                     On August 14, 2024, the city issued an Invitation to Bid; five bids were received.

§                     State Utility Contractors was selected as the lowest responsive, responsible bidder.

§                     On August 11, 2021, City Council approved a developer reimbursement agreement with Crescent River District, LLC to fund construction of the Beaverdam Creek Trunk Sewer Phase 2. This contract fulfills the city’s agreement with Crescent River District.

§                     The project is anticipated to be complete by second quarter 2025.

 

Charlotte Business INClusion

Established MBE Goal: 8.00%

Committed MBE Goal: 1.76%

State Utility Contractors failed to meet the established contract goal but earned the required minimum Good Faith Efforts. State Utility Contractors has committed 1.76% ($22,786) of the total contract amount to the following certified firm(s):

§                     CriTek Engineering Group, PC (MBE, SBE) ($6,786) (CCTV sewer)

§                     Mid-Atlantic Erosion Control, Inc. (MBE, SBE) ($6,000) (erosion control)

§                     Silverback Brothers, LLC (MBE, SBE) ($10,000) (hauling)

 

Established WBE Goal: 3.00%

Committed WBE Goal: 1.63%

State Utility Contractors failed to meet the established contract goal but earned the required minimum Good Faith Efforts. State Utility Contractors has committed 1.63% ($21,100) of the total contract amount to the following certified firm(s):

§                     CES Group Engineers LLP (WBE) ($21,100) (surveying)

 

Fiscal Note

Funding:  Charlotte Water Capital Investment Plan

 