Legislation Details

File #: 15-26026    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 4/8/2026 In control: City Council Business Meeting
On agenda: 6/8/2026 Final action: 6/8/2026
Title: Arrowood Road at Whitehall Commons Center Drive Intersection Improvements
Attachments: 1. Map - Arrowood Rd Intersection Improvements

Title

Arrowood Road at Whitehall Commons Center Drive Intersection Improvements

 

Action

Action:                       

A.                     Reject the low bid submitted by Cardinal Civil Contracting, LLC for the Arrowood Road at Whitehall Commons Center Drive Intersection Improvements project, and

 

B.                     Approve a contract in the amount of $1,255,340.57 to the lowest responsive, responsible bidder DOT Construction, Inc. for the Arrowood Road at Whitehall Commons Center Drive Intersection Improvements project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Kathleen Cishek, General Services

Keith Bryant, General Services

 

Explanation

§                     This project will construct intersection improvements at Arrowood Road and Whitehall Commons Center Drive to enhance mobility and safety in Council District 3.

§                     Improvements include installation of a new traffic signal, pedestrian signals, roadway widenings, curb ramps, and crosswalks.

§                     On March 10, 2026, the city issued an Invitation to Bid; five bids were received.

§                     DOT Construction, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the first quarter of 2028.

 

Reject Low-Bid Explanation

The low bid from Cardinal Civil Contracting, LLC in the amount of $1,254,304.18 was found to be non-responsible/non-responsive for failure to meet the established WSBE goal and failure to satisfy the Good Faith Efforts requirements.

 

Charlotte Business INClusion

Established MBE Goal: 5.00%

Committed MBE Goal: 8.01%

DOT Construction, Inc. exceeded the established contract goal and has committed 8.01% ($100,568) of the total contract amount to the following certified firm(s):

§                     DMD Supply Services Group LLC (MBE, SBE) ($37,800) (material)

§                     Streeter Trucking Company (MBE, SBE) ($62,768) (hauling)

 

Established WSBE Goal: 10.00%

Committed WSBE Goal: 10.00%

DOT Construction, Inc. met the established contract goal and has committed 10.00% ($125,535) of the total contract amount to the following certified firm(s):  

§                     Clear Creek of Salisbury Inc. (WBE, SBE) ($125,535) (concrete)

 

Fiscal Note

Funding: General Capital Investment Plan

 

Attachments

Attachment(s)

Map