Title: Construct Sardis Road North Sidewalk
Attachments: 1. Map - Sardis Road North Sidewalk

Title

Construct Sardis Road North Sidewalk

 

Action

Action                     

A.                     Reject the low bid submitted by Carolina Prime Developers, LLC (SBE) for the Sardis Road North Sidewalk, and

 

B.                     Approve a contract in the amount of $1,444,390.70 to the lowest responsive, responsible bidder DOT Construction, Inc. (SBE) for the Sardis Road North Sidewalk project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Kathleen Cishek, General Services

Keith Bryant, General Services

 

Explanation

§                     The Sardis Road North Sidewalk project was identified in the Sidewalk and Pedestrian Safety Program and will improve safety, connectivity, and pedestrian mobility in Council District 6.

§                     This contract includes construction of approximately 0.5 miles of sidewalk along Sardis Road North from Ritter Drive to Rittenhouse Circle.

§                     Work will also include storm drainage, bus waiting pads, curb ramps, curb and gutter, and planting strips.

§                     On June 13, 2024, the city issued an Invitation to Bid; seven bids were received.

§                     DOT Construction, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the second quarter of 2026.

 

Reject Low-Bid Explanation

The bid from Carolina Prime Developer, LLC in the amount of $981,342.45 did not meet the North Carolina General Statutes and was found to be non-responsive.

 

Charlotte Business INClusion

Established MBE Goal: 6.00%

Committed MBE Goal: 6.00%

DOT Construction, Inc met the established contract goal and has committed 6.00% ($86,664) of the total contract amount to the following certified firm(s):

§                     Streeter Trucking Company (MBE, SBE) ($86,664) (hauling)

 

Established WBE Goal: 4.00%

Committed WBE Goal: 4.00%

DOT Construction, Inc met the established contract goal and has committed 4.00% ($57,776) of the total contract amount to the following certified firm(s):

§                     Clear Creek of Salisbury Inc. (WBE, SBE) ($57,776) (concrete)

 

Fiscal Note

Funding:  General Capital Investment Plan

 

Attachments