Title: Construction Change Order #1 for the Charlotte-Mecklenburg Police Department South Division Station
Attachments: 1. Map_Construct Change Order #1 for CMPD South Division Station.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Construction Change Order #1 for the Charlotte-Mecklenburg Police Department South Division Station

 

Action

Action: 

Approve change order #1 in the amount of $645,866.07 to Barnhill Contracting Company for the Charlotte-Mecklenburg Police Department South Division Station project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Jennifer Smith, General Services

John Mrzygod, General Services

Explanation

§                     This project will construct a 16,000-square-foot facility at 11217 Providence Road West in Council District 7.

§                     A section of this facility is dedicated for staff from the Code Enforcement Division of Housing and Neighborhood Services (HNS).

§                     Change order #1 in the amount of $645,866.07 is needed to fund the following:

-                     After value engineering efforts, there were multiple bid items which came in above estimates including masonry, HVAC, and exterior wall panels ($316,000),

-                     Additional 1,100 square foot storage facility needed for both Charlotte-Mecklenburg Police Department and HNS to store equipment, utility vehicles, and maintenance equipment ($204,000), and

-                     Items initially value engineered out of the contract are being added back due to better pricing and schedule including signage and interior trim/counters/cabinets ($125,866.07).

§                     On September 23, 2019, City Council authorized the City Manager to negotiate and approve a Construction Manager at Risk contract in the amount up to $11,500,000 to Barnhill Contracting Company.

§                     The new total value of the contract including change order #1 will be $12,145,866.07

§                     The project is scheduled to be complete by first quarter 2021.

 

Charlotte Business INClusion

Original Established M/SBE Goal: 22%

Original Committed M/SBE Goal: 22%

M/SBE Attained Goal to Date: 28.79%

 

Prime exceeded the established subcontracting goal, including this Change Order, committing 28.79% ($3,496,795) of the total contract amount (Part D: Section 6 of the Charlotte Business INClusion Policy).

 

Fiscal Note