File #: 15-5381    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 3/30/2017 In control: City Council Business Meeting
On agenda: 5/8/2017 Final action: 5/8/2017
Title: Electrical Power System Improvements and Generator Replacement Project
Attachments: 1. Mallard Creek WWTP Map, 2. Lee S. Dukes WTP Map

Title

Electrical Power System Improvements and Generator Replacement Project 

 

Action

Action                     

Approve a contract with Southeastern Consulting Engineers, Inc. to provide professional engineering services for:

 

-                     Lee S. Dukes Water Treatment Plant Generator  project in the amount of $521,098, and

 

-                     Mallard Creek Wastewater Treatment Plan Generator project in the amount of $658,224.  

 

Body

Staff Resource(s):

Barry Gullet, Charlotte Water

Ron Hargrove, Charlotte Water

 

Explanation

§                     The contract with Southeastern Consulting Engineers, Inc. will provide professional engineering services for the replacement of the existing generator systems, related equipment, and structures at the Lee S. Dukes water treatment plant and the Mallard Creek wastewater treatment plant.

§                     The current generators at the plants do not provide sufficient power for the pumps to run at their full capacities, which is essential to support current and future water demands.

§                     On December 16, 2016, the City issued a Request for Qualifications (RFQ) for Professional Engineering Services for Standby Generator Facilities. In response to the RFQ, the City received four proposals from interested professional service providers for the Standby Generator Facility at the Mallard Creek WWTP and three proposals from interested professional service providers for the Standby Generator Facility at the Lee S. Dukes WTP.

§                     Southeastern Consulting Engineers, Inc. is the best qualified firm to meet the City’s needs for both projects on the basis of demonstrated competence and qualification of professional services in response to the RFQ requirements.

§                     Charlotte Water will bring forth a contract for construction administration services in fall 2018.

 

Charlotte Business INClusion

The City negotiated subcontracting participation after the proposal selection process (Part C: Section 2.1 (h) of the Charlotte Business INClusion Policy).  Southeastern Consulting Engineers, Inc., a City SBE, committed $41,621 or 3.52% of the total contracts to the following certified firms: 

 

Lee S. Dukes Water Treatment Plant Contract

§                     Capstone Civil Group, PA (MBE, SBE) ($9,654) (geotechnical)

§                     Dunbar Geomatics Group, PLLC (SBE) ($6,875) (surveying and underground locates)

§                     Maloney Engineering (SBE) ($2,500) (mechanical engineering)

 

Mallard Creek Wastewater Treatment Plant Contract

§                     Dunbar Geomatics Group, PLLC (SBE) ($10,455) (surveying and underground locates)

§                     Capstone Civil Group, PA (MBE, SBE) ($9,637) (geotechnical)

§                     Maloney Engineering (SBE) ($2,500) (mechanical engineering)

 

Fiscal Note

Funding:  Charlotte Water Community Investment Plan

 

 