Title: Morris Field Drive Bridge Replacement Project Supplemental Agreements
Attachments: 1. Map - Morris Field Drive Bridge Replacement Project, 2. Resolution - Action A, 3. Resolution - Action B, 4. Budget Ordinance - Morris Field Drive Bridge Replacement Project

Title
Morris Field Drive Bridge Replacement Project Supplemental Agreements

 

Action ion

Action

A.                     Adopt a resolution authorizing the City Manager to negotiate and execute a Supplemental Agreement with the North Carolina Department of Transportation to accept Surface Transportation Block Grant Direct Attributable funds in the amount of $1,745,000 for the Morris Field Drive Bridge Replacement Project,

 

B.                     Adopt a resolution authorizing the City Manager to negotiate and execute a Supplemental Agreement with the North Carolina Department of Transportation to accept Surface Transportation Block Grant funds in the amount of $857,000 for the Morris Field Drive Bridge Replacement Project, and

 

C.                     Adopt a budget ordinance appropriating $2,602,000 from the North Carolina Department of Transportation to the General Capital Projects Fund.

 

Body

Staff Resource(s):

Debbie Smith, Transportation

Samantha Miller, Transportation

Phil Reiger, General Services

Kathleen Cishek, General Services

 

Explanation

§                     The Morris Field Drive Bridge Replacement Project will replace a bridge over Norfolk Southern Railroad near Wilkinson Boulevard.

§                     This project will also include street lighting, bike lanes, and sidewalks.

§                     The project supports the Strategic Mobility Plan adopted by City Council in June 2022 by advancing a safe transportation system for all users.

§                     In 2015, City Council authorized the City Manager to execute a municipal agreement with the North Carolina Department of Transportation (NCDOT) in the amount of $2,480,000 for the bridge replacement project.

§                     This project will receive an additional $1,745,000 in Surface Transportation Block Grant funds from NCDOT, with a local match of $1,736,844 for construction.

§                     This project will receive an additional $857,000 in Surface Transportation Block Grant funds from NCDOT. NCDOT recognized that inflation was affecting project design costs and agreed to provide a one-time funding increase to cover an overage in design fees.

§                     The project funding distribution is as follows:

-                     NCDOT: $5,082,000

§                     Surface Transportation Block Grant (2015 original): $2,480,000

§                     Surface Transportation Block Grant (2024 supplemental): $857,000

§                     Surface Transportation Block Grant Discretionary Allowance: $1,745,000

-                     City of Charlotte: $7,606,844

§                     Bridge Program: $2,606,844

§                     Anticipated 2024 Transportation Bonds: $5,000,000

§                     This project is located in Council District 3.

§                     Construction for the project is anticipated to begin in fiscal year 2026.

§                     The format of these supplemental agreements is consistent with past municipal agreements between the city and NCDOT.

 

Fiscal Note

Funding: NCDOT Surface Transportation Block Grant

 