Title
Parkwood Phase 1 Storm Drainage Improvement Project Change Order
Action
Action:
Approve change order #1 for $456,500 to Sealand Contractors, Corp. for the Parkwood Storm Drainage Improvement project.
Body
Staff Resource(s):
Susan Tolan, Engineering & Property Management
Explanation
§ The Parkwood Storm Drainage improvement/flood control project includes:
- Four separate culvert installations,
- Storm drainage,
- Channel improvements,
- Sanitary sewer relocations,
- Water line relocations,
- Curb and gutter,
- Sidewalk, and
- Erosion control.
§ On May 27, 2014, the City Council awarded the original contract in the amount of $5,136,776.56.
§ The City deleted the N. Brevard Street culvert installation from the project, resulting in a reduction of approximately $365,000. City Council will be asked to approve a separate construction contract once the proposed redevelopment plans are finalized.
§ Change order #1 in the amount of $456,500 will provide funds to accommodate the following overruns in contract items:
- Rock removal exceeds the quantity that was estimated based on the subsurface analysis.
- Additional backfill material due to the volume of rock encountered and the poorly graded composition of the remaining on-site soil.
- The total amount of rock removal and select material overrun is $821,101.40. Due to the deletion of the N. Brevard Street culvert work from the contract, the entire amount is not included in the change order.
§ The total value of the contract including this change order is $5,593,276.56 and funding is available in the program budget.
§ The project is on schedule to meet the completion date of December 2016.
Background
§ In October 2015, City staff was informed of a private redevelopment plan in the project area. The preliminary redevelopment plans indicated possible removal of a house that if left in place, would require significant work from the City when replacing the culvert at N. Brevard Street.
Charlotte Business INClusion
All additional work involved in this change order will be performed by Sealand Contractors and their existing subcontractors (Part D: Section 6 of the Charlotte Business INClusion Policy).
Fiscal Note
Funding: Storm Water Community Investment Plan