File #: 15-7487    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 1/30/2018 In control: City Council Business Meeting
On agenda: 3/26/2018 Final action: 3/26/2018
Title: Rose Valley Drive Storm Water Improvement Project
Attachments: 1. Location Map - Rose Valley Drive Storm Water Improvement Project

Title

Rose Valley Drive Storm Water Improvement Project

 

Action

Action:

Award a contract in the amount of $1,411,105.30 to the lowest responsive bidder Hall Contracting Corporation for the Rose Valley Drive Storm Water Improvement Project.

 

Body

Staff Resource(s):

Mike Davis, Engineering and Property Management

Stewart Edwards, Engineering and Property Management

 

Explanation

§                     This project will address failing storm drainage systems on Rose Valley Drive, Stonewood Drive and Brookhaven Road. It is located in Council District 6.

§                     Work will include the installation of 1,665 linear feet of concrete pipe, 100 linear feet of pipe lining, associated drainage structures, curb, gutter and asphalt paving.

§                     On January 22, 2018, the City issued an Invitation to Bid; six bids were received from interested service providers.

§                     Hall Contracting Corporation was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be completed in second quarter 2019.

 

Charlotte Business INClusion

Established SBE Goal: 20.00%

Committed SBE Goal: 22.67%

Hall Contracting Corporation exceeded the established subcontracting goal, and has committed 22.67% ($319,897.56) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Trull Contracting (SBE) (asphalt) ($114,794.25)

§                     On Time Construction (SBE, MBE) (concrete) ($70,798.70)

§                     Silverback Brothers (SBE, MBE) (hauling) ($66,338.25)

§                     All Points Trucking (SBE) (hauling) ($41,570.74)

§                     Bird Dog Traffic Control (SBE) (traffic control) ($12,300.62)

§                     Whitesell Trucking (SBE) (clearing/grubbing) ($10,900)

§                     A-1 Precision Fence (SBE) (fencing) ($3,195)

 

Established MBE Goal: 7.00%

Committed MBE Goal: 9.72%

Hall Contracting Corporation exceeded the established subcontracting goal, and has committed 9.72% ($137,136.95) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     On Time Construction (MBE, SBE) (concrete) ($70,798.70)

§                     Silverback Brothers (MBE, SBE) (hauling) ($66,338.25)

 

Fiscal Note

Funding:  Storm Water Community Investment Plan

 