Skip to main content
City of Charlotte Banner
File #: 15-2107    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 12/15/2015 In control: City Council Business Meeting
On agenda: 1/25/2016 Final action: 1/25/2016
Title: LYNX Blue Line Extension - Track and Systems Contract Amendment

Title

LYNX Blue Line Extension - Track and Systems Contract Amendment

 

 

Action

Action:

Approve contract amendment #3 in the amount of $4,500,000 to the LYNX Blue Line Extension Track and Systems contract with Balfour Beatty Infrastructure, Inc. for settlement of all Contractor delay related claims and to amend the contract schedule.

 

Body

Staff Resource(s):

John Lewis, CATS

Jeb Blackwell, Engineering & Property Management

Danny Rogers, CATS

 

Explanation

§                     The Blue Line Extension project has been on an aggressive schedule to implement service as quickly as possible.

§                     In 2014, the Blue Line Extension project experienced significant delays in utility relocation work, which delayed the follow-on civil construction work. Acceleration amendments with the Civil A and Civil B/C contractors were executed in 2015 to partially recover the schedule and to maintain the revenue service opening date for summer 2017.  

§                     Staff has now completed negotiations with the Track and Systems contractor related to those same schedule delays and mitigation efforts. 

§                     Contract amendment #3 in the amount of $4,500,000 will:

-                     Settle all Contractor claims related to delay through December 15, 2015;

-                     Amend the contract schedule accordingly; and

-                     Add incentives for the contractor to meet a projected opening for summer 2017.

§                     The costs associated with this amendment can be accommodated within the current project budget from existing project contingency.

 

Background

§                     On April 14, 2014, the City Council awarded a construction contract to Balfour Beatty Infrastructure Inc. for $130,805,444.31 to perform Track and Systems construction for the Blue Line Extension (BLE) and Blue Line Capacity Expansion project (BLCE).

§                     Nine change orders have been processed to date.  On October 26, 2015, the City Council approved change order #9 in the amount of $7,000,000 for additional work items to be constructed, bringing the current contract value to $137,805,444.31.

§                     On March 9, 2015, contract amendment #1 was approved to allow for payment of stored materials off-site. 

§                     On August 2, 2015, contract amendment #2 was approved to grant access and add an intermediate contract time related to Segment A1.

§                     Contract amendments #1 and #2 were administrative and did not affect the contract value.

§                     Contingent upon approval of contract amendment #3, the new total value of the contract including amendments/change orders will be $142,305,444.31.

 

Disadvantaged Business Enterprise (DBE) Opportunity

Any additional contract scope authorized by this change order will be held to the original contract DBE goal of 9.2%

 

Fiscal Note

Funding:  CATS Community Investment Plan