Title: Airport Concourse D Renovations Construction
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Airport Concourse D Renovations Construction

 

Action

Action                     

A.                     Approve change order #1 for $39,255,742.27 to Messer Construction Co. for Construction Manager at Risk services for the Concourse D Renovations construction project, and

 

B.                     Approve contract amendment #4 for $1,015,273 to the contract with RS&H Architects-Engineers-Planners, Inc. for construction administration services for the construction phase of the Concourse D Renovations project.

 

Body

Staff Resource(s):

Haley Gentry, Aviation

Jack Christine, Aviation

 

Background

§                     The Concourse D Renovations project will provide for a 99,000 square foot renovation of select finishes and amenities on the ticket level of Concourse D, to include concourse corridors, holdrooms, and restrooms.

§                     This project will include a full renovation of restrooms and infrastructure to support charging powered seating, as well as new wall finishes, ceilings, lighting, carpet, and paint.

§                     The project is anticipated to be complete by the first quarter of fiscal year 2027.

 

Explanation

Action A

§                     On July 10, 2023, City Council approved a contract with Messer Construction Co. in the amount of $3,509,420.89 for Construction Manager at Risk (CMAR) services to procure the major mechanical and electrical equipment for the Federal Inspection Station Facility (FIS) and Concourse D Renovations project.

§                     This change order will incorporate the guaranteed maximum price contract for the CMAR for the full construction of the Concourse D Renovations project.

§                     The new total value of the contract is $42,765,163.16.

 

Action B

§                     On February 24, 2020, City Council approved a contract with RS&H Architects-Engineers-Planners, Inc. in the amount of $4,330,965 to provide design services for the FIS and Concourse D Renovations project.

§                     Contract amendment #1 in the amount of $438,570 was for additional design services for relocating the FBI suite, a new electrical room and baggage carousel, and automatic tag readers.

§                     Contract amendment #2 in the amount of $496,136 was for dividing the original scope of work into three bid packages and construction administration services for Package 1.

§                     Contract amendment #3 in the amount of $137,005 was for re-scoping Package 2 and construction administration for fire alarm improvements.

§                     Amendment #4 includes construction administration services for Package 2, including design-related items such as submittal reviews, Requests for Information responses, as-built final drawings, and material acceptance.

§                     The new value of the contract including all amendments is $6,417,949.

 

Charlotte Business INClusion

Action A

The city has negotiated an overall project goal of 9.50% MBE and 2.00% SBE. Because this is a Construction Manager at Risk, the Construction Manager has the opportunity to add Minority-owned Business Enterprises (MBE), Women-owned Business Enterprises (WBE) or Small Business Enterprise (SBE) firms throughout the life of the Project.

 

Messer Construction Co. has committed 48.85% ($19,175,895) of the total contract Change Order amount to the following certified firm(s):

§                     A&D Express Trucking LLC (MBE, SBE) ($4,200) (hauling)

§                     ADA Contracting, LLC (MBE, SBE) ($61,250) (plumbing materials)

§                     AEGJ Construction LLC (MBE, SBE) ($143,125) (final clean, painting)

§                     Bergman Brothers Staffing (MBE) ($100,000) (general labor)

§                     Besco Electrical Corporation (MBE) ($9,075,000) (electrical)

§                     Carrothers Enterprise (MBE) ($102,000) (carpet materials)

§                     DMD Supply Services Group LLC (MBE, SBE) ($19,570) (concrete procurement)

§                     Express Logistics Services, Inc (MBE, SBE) ($56,850) (furnish aggregates, hauling)

§                     Firestop Carolinas Inc (WBE) ($13,000) (fire stop)

§                     Five Boys Trucking (MBE, SBE) ($37,350) (hauling)

§                     G&Y Masonry, Inc (MBE) ($65,500) (masonry)

§                     GP Supply Company LLC (MBE) ($61,250) (plumbing materials)

§                     Sterling Construction Services (MBE) ($822,900) (general trades)

§                     Superior Mechanical Systems, Inc (MBE) ($7,131,900) (HVAC)

§                     United Painting Services, Inc (MBE, SBE) ($1,482,000) (metal framing and drywall)

 

Action B

All additional work involved in this Amendment will be performed by the RS&H Architects-Engineers-Planners, Inc. and their existing subcontractors. RS&H Architects-Engineers-Planners, Inc. has committed 26.39% ($267,890) of the total contract Amendment amount to the following certified firm(s):

§                     The Wilson Group (SBE) ($267,890) (architectural design)

 

Fiscal Note

Funding:  Aviation Capital Investment Plan