File #: 15-2556    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 2/10/2016 In control: City Council Business Meeting
On agenda: 3/28/2016 Final action: 3/28/2016
Title: Eastcrest Drive Storm Drainage Improvement Project
Attachments: 1. Location Map - Eastcrest Drive Storm Drainage Improvement Project

Title

Eastcrest Drive Storm Drainage Improvement Project

 

Action

Action:                       

Award a contract in the amount of $667,263.30 to the lowest responsive bidder United of Carolinas, Inc. for the Eastcrest Drive Storm Drainage Improvement project.

 

Body

Staff Resource(s):

Stewart Edwards, Engineering & Property Management

 

Explanation

§                     The Storm Water repair project will improve the storm drainage infrastructure in the 1700 block of Eastcrest Drive by upgrading and realigning the existing storm drainage system.  This system conveys stormwater into Briar Creek from Eastcrest Drive, Wembley Drive, and multiple adjacent properties.

§                     The project is located off Central Avenue in the vicinity of Briar Creek Road and Commonwealth Avenue.

§                     The work will include:

-                     Storm drainage replacement;

-                     Installation of box culvert;

-                     Curb, gutter, and sidewalk replacement;

-                     Driveway replacement; and

-                     Asphalt pavement replacement.

§                     On December 28, 2015, the City issued an Invitation to Bid for the Eastcrest Drive Storm Drainage Improvement project; ten bids were received from interested service providers.

§                     United of Carolinas, Inc. was the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by March 2017.

 

Charlotte Business INClusion

Established SBE Goal: 16.00%

Committed SBE Goal: 20.68%

United of Carolinas, Inc. exceeded the established SBE subcontracting goal, and has committed 20.68% ($138,000) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

                     B & N Grading, Inc. (SBE) ($95,000) (asphalt and hauling)

                     Streeter Trucking Company, Inc. (SBE, MBE) ($41,000) (hauling)

                     R.R.C. Concrete Inc (SBE) ($2,000) (concrete)

 

Established MBE Goal: 6.00%

Committed MBE Goal: 6.14%

United of Carolinas, Inc. exceeded the established MBE subcontracting goal, and has committed 6.14% ($41,000) of the total contract amount to the following certified firm (Part B: Section 3 of the Charlotte Business INClusion Policy):

                     Streeter Trucking Company, Inc. (SBE, MBE) ($41,000) (hauling)

 

Fiscal Note

Funding:  Storm Water Community Investment Plan

 

Attachments

Attachment

Map