Title: Professional Services for Strategic Mobility Plan

Title

Professional Services for Strategic Mobility Plan

 

Action

Action:

A.                     Approve contracts for owner advisor, program management support and augmentation, and program/project controls and risk management support for a term of three years with the following:

-                     AtkinsRealis, USA, Inc.,

-                     Infrastructure Strategies, LLC., and

 

B.                     Authorize the City Manager to renew the contracts for up to two, one-year renewal terms with possible price adjustments and to amend the contracts consistent with the purpose for which the contracts were approved.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Kathleen Cishek, General Services

Debbie Smith, Transportation

Justin Carroll, Transportation

 

Explanation

§                     The Strategic Mobility Plan, adopted by City Council on June 27, 2022, is centered on the goal of providing safe, connected, and equitable mobility. This Plan aligns the city’s mobility strategy with the Charlotte Future 2040 Comprehensive Plan.

§                     The city is seeking to award professional services on-call contracts to provide expert guidance, oversight, and support of strategic plan projects in three of the following areas:

-                     Owner advisor support,

-                     Program management support, and

-                     Program/project controls and risk management.

§                     On February 14, 2025, the city issued a Request for Qualifications (RFQ); 18 responses were received.

§                     The companies selected best meet the city’s needs in terms of qualifications, experience, and responsiveness to the RFQ requirements.  

§                     At renewal, potential price adjustments may be considered based on legitimate and justified increases in the cost of doing business. The ability to consider price adjustments also allows the city to accept decreases, if warranted.

§                     Annual aggregate expenditures are estimated to be $2,350,000.

 

Charlotte Business INClusion

The city negotiates contract participation after the proposal selection process. On these contracts, the prime consultants have each committed 10.00% (6.00% MBE, 4.00% WBE/SBE) of the total contract amount to the following certified firm(s):

AtkinsRealis USA, Inc.

§                     BB Foster Consulting (MBE, SBE)

§                     BLWall Consulting (MBE, SBE)

§                     Integra Design Group (MBE)

§                     The Wonder Group, LLC (MBE)

 Infrastructure Strategies, LLC (SBE)

§                     Amplify Consulting, LLC (MBE, SBE)

§                     Motivation Marketing Firm (MBE)


Fiscal Note

Funding:  General Capital Investment Plan