Legislation Details

File #: 15-26080    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 4/16/2026 In control: City Council Business Meeting
On agenda: 5/26/2026 Final action:
Title: Woodlawn Elevated Storage Tank Construction and Construction Administration Services
Attachments: 1. Woodlawn Elevated Storage Tank
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Woodlawn Elevated Storage Tank Construction and Construction Administration Services

 

Action

Action:

A.                     Approve a contract in the amount of $19,501,650 to the lowest responsive, responsible bidder Caldwell Tanks, Inc. for the Woodlawn Elevated Storage Tank Project, and

 

B.                     Approve contract amendment #2 for $1,569,828 to the contract with Black & Veatch International Company for construction administration services for the Woodlawn Elevated Storage Tank Project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Chuck Bliss, Charlotte Water

 

Explanation

§                     This project is located at the intersection of South Tryon Street and Woodlawn Road in Council District 3 and will provide a more reliable water supply and improved water quality.

 

Action A

§                     This contract will construct a 3,000,000-gallon elevated water tank and will install approximately 1,340 linear feet of 36-inch waterline and 461 linear feet of 12-inch waterline to feed the tank. 

§                     On March 19, 2026, the city issued an Invitation to Bid (ITB); two bids were received.

-                     NC General Statute Section 143-132 prohibits municipalities from awarding construction contracts over $500,000 without receiving at least three competitive bids from the initial advertisement of the contract. The city may subsequently award the contract even if readvertisements result in fewer than three competitive bids.

§                     On April 22, 2026, the ITB was reissued; two bids were received.

§                     Caldwell Tanks, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the first quarter of 2029.

 

Action B

§                     On March 22, 2021, following a competitive solicitation process, the city entered into a contract with Black & Veatch International Company for $1,592,060 for design services for the Sunset, Woodlawn, and Mint Hill Elevated Storage Tank projects.

-                     Amendment #1 is for construction administration services for the Woodlawn Elevated Storage Tank Project, including but not limited to inspection, materials testing, and blast monitoring.

§                     The new estimated value of the contract including this amendment is $4,506,736.

 

Charlotte Business INClusion

Action A

Established MWSBE Goal: 2.00%

Committed MWSBE Goal: 2.51%

Caldwell Tanks, Inc. exceeded the established contract goal and has committed 2.51% ($488,808) of the total contract amount to the following certified firm(s):

§                     B&N Grading (WBE) ($340,000) (asphalt and road)

§                     Diamond Trucking of NC Inc. (MBE, SBE) ($76,000) (hauling)

§                     Serene Landscape Consulting LLC (MBE, SBE) ($72,808) (landscape)

 

Action B

All additional work involved in this amendment will be performed by the Black & Veatch International Company and their existing subconsultants:

§                     Habitat Assessment and Restoration Professionals (WBE, SBE) (environmental services)

§                     Richa Graphics (MBE, SBE) (reprographics)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 

Attachments

Attachment(s)

Map