City of Charlotte Banner
File #: 15-23110    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 8/5/2024 In control: City Council Business Meeting
On agenda: 10/14/2024 Final action: 10/14/2024
Title: CATS New Bern Drainage Repair Project
Attachments: 1. Map - CATS New Bern Drainage Repair Project

Title

CATS New Bern Drainage Repair Project

 

Action

Action                     

A.                     Approve a contract in the amount of $2,027,666.74 to the lowest responsive bidder NJR Group, Inc. for the Charlotte Area Transportation System New Bern Drainage Repair project, and

 

B.                     Authorize the City Manager to amend the contract consistent with the purpose for which the contract was approved.

 

Body

Staff Resource(s):

Brent Cagle, CATS

Kelly Goforth, CATS

James Fatula, CATS

 

Explanation

§                     The Charlotte Area Transportation System requires the installation of a new storm drainage (culvert) crossing across the light rail alignment, located between New Bern Station and Poindexter Road in Council District 3.

§                     The new culvert is necessary to provide additional stormwater capacity and resolve ongoing issues that may impact rail infrastructure.  

§                     On July 19, 2024, the city issued an Invitation to Bid; one bid was received.

-                     In accordance with North Carolina General Statute Section 143-132, if three bids are not received from reputable and qualified contractors, the project must be re-advertised. During the re-advertisement, the contract may be awarded to the lowest responsible bidder even if only one bid is received from an interested service provider.

§                     On August 22, 2024, the city issued a second Invitation to Bid; one bid was received.

§                     NJR Group, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the second quarter of 2025.

 

Disadvantaged Business Enterprise

Established DBE Goal: 13.60%

Committed DBE Goal: 13.49%

NJR Group, Inc. did not to meet the established contract goal but demonstrated engagement in adequate Good Faith Efforts in an attempt to meet the goal. NJR Group, Inc. has committed 13.49% ($273,432) of the base bid amount to the following certified firm(s):

§                     RRC Concrete (DBE) ($41,432) (concrete)

§                     CES Group Engineers, LLP (DBE) ($232,000) (engineering)

 

Fiscal Note

Funding:  CATS Capital Investment Plan

 

Attachments

Attachment(s):

Map