McMullen Creek Tributary Construction Services

 

Action

Action:

Approve a guaranteed maximum price of $9,178,204.55 to Atlantic Coast Contractors, Inc. for Design-Build construction services for the McMullen Creek Tributary-Quail Hollow Segment Sanitary Sewer Replacement, Rehabilitation, and Repair project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     Atlantic Coast Contractors, Inc. has developed a guaranteed maximum price (GMP) for the replacement, rehabilitation, and repair of the McMullen Creek Tributary-Quail Hollow segment sanitary sewer line.

§                     This segment will relocate approximately 4,300 linear feet of eight-inch gravity sanitary sewer flowing from Gleneagles Road, along a McMullen Creek tributary stream and the Quail Hollow Golf Course, to the McMullen Creek Interceptor (Council District 6).

§                     On January 14, 2019, City Council approved a contract with Atlantic Coast Contractors, Inc. for Design-Build design services. Based on the design, a GMP for construction services was developed.

§                     As part of the design, budgeting, and property owner negotiation process, the project construction is phased.

§                     On January 27, 2020, City Council approved a contract with Atlantic Coast Contractors, Inc. for construction of the first segment of the McMullen Creek Tributary Sanitary Sewer Replacement, Rehabilitation, and Repair project.

§                     This project segment is anticipated to be complete by second quarter 2022.

 

Charlotte Business INClusion

The city negotiates participation for Design-Build contracts after the firm is selected and scopes of work are defined for design and construction services (Part G: Section 2.7 of the Charlotte Business INClusion Policy). Atlantic Coast Contractors, Inc. has committed $1,260,700 or approximately 13.74% of the total contract for Design-Build construction services to the following certified firms:

§                     Gavel & Dorn Engineering, PLLC (SBE) ($373,000) (engineering services)

§                     Central Carolina Underground (SBE) ($265,000) (manhole rehab)

§                     Right of Way Contractors, LLC (SBE) ($250,000) (paving and concrete)

§                     Venture Utility Construction, Inc. (SBE) (150,000) (utility construction)

§                     P & H Utilities (SBE) ($100,000) (public utilities)

§                     Streeter Trucking Company (MBE, SBE) ($30,000) (hauling)

§                     Mid Atlantic Erosion Control Inc (MBE, SBE) ($30,000) (erosion control)

§                     Landtec (SBE) ($22,400) (surveying)

§                     CriTek Engineering Group, P.C. (MBE, SBE) ($18,000) (erosion control inspections)

§                     Jones Grading and Fencing Inc. (SBE) ($10,000) (hauling)

§                     Pipe Pros, LLC (SBE) ($10,000) (video and cleaning of sewer service lines)

§                     Carolina Wetland Services, Inc. (WBE, SBE) ($2,300) (wetland services)

 