Title: LYNX Blue Line Grade Crossing Repair
Attachments: 1. SouthBlvdNorthGradeCrossingRepairMap

Title

LYNX Blue Line Grade Crossing Repair

 

Action

Action:                     

Award a contract in the amount of $776,953 to the lowest responsive bidder Bullock Construction, Inc. for the repair of the South Boulevard North grade crossing of the LYNX Blue Line.

 

Body

Staff Resource(s):                     

Allen Smith, CATS                                          

Bong Vang, CATS

 

Explanation

§                     The LYNX Blue Line intersects with several public roads along its length - some of which are ‘at-grade’ crossings. 

-                     An ‘at-grade’ crossing is a crossing in which the intersecting rail and roadway are of the same elevation and controlled with standard railroad signals and crossing gates.

§                     A recent inspection indicated that the at-grade crossing of the rail alignment at South Boulevard North is in need of the following repairs:

-                     The grade crossing panels are starting to settle and are not at the same elevation as the road.  The settlements in the panels are causing warping of the rail.

§                     The existing panels will be removed and evaluated to determine if the panels can be reused as part of the repair or require replacement.

§                     The soil and stone under the panels will be repaired prior to the placement of the panels.

-                     The storm drainage along the grade crossing will be improved and the pavement markings will be improved for better traffic control.

§                     On July 1, 2015, an Invitation to Bid for grade crossing repairs was issued; two bids were received at an amount far in excess of the engineer’s estimate and available budget.  As a result, staff reengineered the project. 

§                     On September 4, 2015, an Invitation to Bid for grade crossing repairs using the reengineered specifications was issued; one bid was received from an interested service provider.

§                     In accordance with North Carolina General Statute 143-132(a), the project was re-advertised on September 9, 2015; two bids were received by interested service providers.

§                     Bullock Construction, Inc. was the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by June 30, 2016.

 

Disadvantaged Business Enterprise

Established DBE Goal: 10%

Committed DBE Goal: 85.2%

Bullock Construction, Inc., a DBE firm, exceeded the established DBE goal and committed 85.2% ($661,953) of the total contract to the following certified firm.

                     Bullock Construction, Inc (DBE) ($661,953)

                     The federal DBE program counts the participation of all DBE contractors working on a contract, without regard to their status as a prime contractor or subcontractor. 

 

Fiscal Note

Funding:  CATS Community Investment Plan

 

Attachments