17. Set a Public Hearing on an Extension of the Temporary
Moratorium on New Telecommunications and Data Storage
Facilities
Action:
Set a public hearing for October 12, 2026, on an extension of the 150-day temporary
moratorium on the acceptance, processing, and approval of applications for new
telecommunications and data storage facilities within the City of Charlotte, North Carolina, and
its Extraterritorial Jurisdiction, pursuant to NC General Statute 160D-107.
Staff Resource(s):
Alyson Craig, City Manager’s Office
Heather Bolick, Special Initiatives
Terrie Hagler-Gray, City Attorney’s Office
Explanation
§
The Charlotte Unified Development Ordinance (UDO) defines a data center as a
“telecommunications and data storage facility, accessed only by employees, that houses computer
systems and associated components, related to the transmittal and receiving of information,
including but not limited to, telecommunications systems, telecommunication and telephone
switching systems, cloud storage systems, and server farms.”
§
Per the UDO, telecommunications and data storage facilities (data centers) are permitted uses by
right in the following zoning districts:
-
-
-
-
-
-
-
General Commercial (CG),
Regional Commercial (CR),
Office Flex Campus (OFC),
Research Campus (RC),
Manufacturing & Logistics (ML-1 and ML-2),
Innovation Mixed Use (IMU), and
Uptown Core (UC).
§
§
Currently all data centers, regardless of size, type, or capacity, are treated the same under the
UDO.
Data centers are subject to applicable zoning and general development standards (setbacks,
height, transparency, landscape yards, screening, exterior lighting, etc.) but have no additional
prescribed conditions.
§
§
At the April 27, 2026, Business Meeting, City Council directed staff to provide information on the
status of data centers in Charlotte.
On May 11, 2026, city staff shared the following with City Council:
-
-
-
-
The existing data center inventory in Charlotte;
Environmental impacts of data centers (water usage, energy consumption, noise);
Jobs and economic development considerations; and
Legal constraints with modifying certain land use requirements in the UDO due to Session
Law 2024-57 (SB 382) which limits the ability of local governments to down-zone property
without the written consents of all affected property owners.
§
At the May 11, 2026, Council Business Meeting, City Council adopted the following
recommendations made by staff:
-
Conduct a public hearing on May 26, 2026, to consider the adoption of a 150-day temporary
moratorium on data centers to begin on June 8, 2026; and
Refer the issue of data centers to the Transportation, Planning, and Development
Committee on June 1.
-
§
§
On May 26, 2026, City Council held a properly noticed legislative public hearing on the proposed
moratorium in accordance with NC General Statute Section 160D-601(b).
The purpose of the temporary moratorium is to allow the city to analyze and study the unique
development, infrastructure, and environmental impacts of data centers and prepare and consider
appropriate regulatory and policy changes to address those impacts. These considerations include,
but are not limited to, impacts on water consumption, energy demand, noise, and land-use
compatibility.