Title
Clarke Creek Pump Station and Forcemain Construction
Action
Action:
Approve a guaranteed maximum price of $5,649,894.00 to State Utility Contractors, Inc. for Design-Build construction services for the Clarke Creek Pump Station and Forcemain project.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Carl Wilson, Charlotte Water
Explanation
§ State Utility Contractors, Inc. has developed a guaranteed maximum price (GMP) for design services, procurement of materials, and construction related to the proposed Clarke Creek Pump Station and associated improvements, located in the Town of Huntersville (adjacent to Council Districts 2 and 4).
§ On February 14, 2022, City Council approved a contract for $5,668,010 with State Utility Contractors, Inc. for Design-Build design services.
§ City Council will receive future requests for the approval of additional GMPs for construction once established.
Charlotte Business INClusion
The city negotiates subcontracting participation for Design-Build contracts after the firm is selected and scopes of work are defined for design and construction services (Part G: Section 2.4 of the Charlotte Business INClusion Policy). State Utility Contractors, Inc. has committed $610,680 or approximately 10.81% of the total contract for construction services to the following certified firms:
§ Fuller and Co. Construction, LLC (SBE) ($419,820) (bore and jack)
§ Sanders Constructors (SBE) ($61,450) (clearing)
§ CES Group Engineers, LLP (SBE, WBE) ($48,500) (site layout and benchmark staking)
§ Soggy Bottom Erosion Control, LLC (SBE) ($37,120) (erosion control)
§ Smart Electric Company, Inc. (WBE) ($28,570) (electrical construction)
§ CITI, LLC (MBE) ($15,220) (instrumentation/SCADA)
Fiscal Note
Funding: Charlotte Water Capital Investment Plan
Attachments
Attachment(s)
Map