Title: Fourth Parallel Runway - Early Grading Construction and Construction Materials Testing Services
Title
Fourth Parallel Runway - Early Grading Construction and Construction Materials Testing Services

Action
Action:
A. Approve a contract in the amount of $44,589,894.76 to the lowest responsive bidder ES Wagner Company, LLC for the Fourth Parallel Runway - Early Grading project,

B. Approve a contract in the amount of $650,000.00 with S&ME, Inc. for construction materials testing and special inspection services in support of the Early Grading for the Fourth Parallel Runway program, and

C. Authorize the City Manager to amend the contract with S&ME, Inc. consistent with the purpose for which the contract was approved.

Body
Staff Resource(s):
Haley Gentry, Aviation
Jack Christine, Aviation

Background
* Aviation is currently in the preliminary design phase for the Fourth Parallel Runway Program with Aviation Consulting Engineers, LLC, which will enhance airfield capacity and operational efficiency.
* This activity is occurring on airport property.

Explanation
Action A
* This Program consists of numerous individual construction projects. This contract will provide grading activities, such as excavation, hauling, and movement of approximately 2,000,000 cubic yards of material from the future runway footprint into three designated stockpiles.
* The work includes grading, drainage, fencing, erosion and sediment control, tree clearing, temporary traffic control, sanitary sewer installation, a concrete box culvert extension, and duct bank installation.
* On January 9, 2023, the city issued an Invitation to Bid; four bids were received.
* ES Wagner Company, LLC was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by fourth quarter 2025.

Actions B & C
* This contract will provide for quality assurance testing of materials for the Early Grading and Stockpiling construction activities.
* Testing will be performed in general accordance with the applicable FAA, ASTM and/or industry standards, unless noted otherw...