File #: 15-19325    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 12/6/2022 In control: City Council Business Meeting
On agenda: 2/27/2023 Final action: 2/27/2023
Title: Traffic Signal Installation and Maintenance

Title

Traffic Signal Installation and Maintenance

 

Action

Action                     

Approve a three-year contract in the amount of $9,195,553.19 to the lowest responsive bidder ALS of North Carolina, Inc. for Unspecified Traffic Signal Installation and Maintenance.

 

Body

Staff Resource(s):

Debbie Smith, Transportation

David Smith, Transportation

Anthony Tagliaferri, Transportation

 

Explanation

§                     The Charlotte Department of Transportation (CDOT) operates and maintains a transportation system that includes traffic signals and supporting infrastructure to manage traffic operations throughout the city.

§                     CDOT maintains traffic signals at over 900 intersections across the city.

§                     Charlotte’s population growth and new development increase the demand for new and modified traffic signals and infrastructure.

§                     This traffic signal contract will provide resources to install and maintain traffic signals and support infrastructure citywide.

§                     On October 14, 2022, the city issued an Invitation to Bid (ITB); two bids were received.

-                     NC General Statute Section 143-132 prohibits municipalities from awarding construction contracts over $500,000 without receiving at least three competitive bids from the initial advertisement of the contract.  The city may subsequently award the contract even if re-advertisements result in fewer than three competitive bids.

§                     On December 1, 2022, the ITB was re-issued; three bids were received.

§                     ALS of North Carolina, Inc. was selected as the lowest responsive, responsible bidder.

 

Charlotte Business INClusion

Established MBE Goal: 3.00%

Committed MBE Goal: 0.00%

 

ALS of North Carolina, Inc. failed to meet the established MBE goal; subsequently a waiver of Good Faith Efforts was granted (Part B: Section 6.2 of the Charlotte Business INClusion Policy).

 

Established SBE Goal: 6.00%

Committed SBE Goal: 2.78%

 

ALS of North Carolina, Inc. failed to meet the established SBE goal; subsequently a waiver of Good Faith Efforts was granted (Part B: Section 6.2 of the Charlotte Business INClusion Policy). However, ALS of North Carolina, Inc. has committed 2.78% ($255,300) of the total contract amount to the following SBE certified firm(s):

§                     Striping Concepts, LLC (SBE) ($255,300) (pavement markings)

 

Fiscal Note

Funding:  General Capital Investment Plan