City of Charlotte Banner
File #: 15-18777    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 9/12/2022 In control: City Council Business Meeting
On agenda: 6/12/2023 Final action: 6/12/2023
Title: Goose Creek Sanitary Sewer Extension to Cresthill Drive
Attachments: 1. Map - Goose Creek Sanitary Sewer Extension to Cresthill Drive

Title

Goose Creek Sanitary Sewer Extension to Cresthill Drive

 

Action

Action                     

Approve a contract in the amount of $1,352,788.80 to the lowest responsive bidder Fuller & Co. Construction, LLC (SBE) for the Goose Creek Sanitary Sewer Extension to Cresthill Drive project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     This contract will provide for the installation of a sanitary sewer pipeline to serve customers located in the Stevens Creek Basin in the Town of Mint Hill (adjacent to Council District 5).

§                     On September 22, 2022, the city issued an Invitation to Bid; six bids were received.

§                     Fuller & Co. Construction, LLC was selected as the lowest responsive, responsible bidder.

§                     On May 22, 2023, Council approved a developer reimbursement agreement with Classic Neighborhood, LLC for $2,400,000 in funding toward the Goose Creek Sanitary Sewer Extension to Cresthill project.

§                     The project is anticipated to be complete by third quarter 2023.

 

Charlotte Business INClusion

Fuller & Co. Construction, LLC is a city certified SBE.

 

Established MBE Goal: 2.00%

Committed MBE Goal: 2.10%

Fuller & Co. Construction, LLC exceeded the established subcontracting goal and has committed 2.10% ($28,345) of the total contract amount to the following certified firm (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Buffkin Trucking, Inc. (MBE, SBE) ($28,345) (hauling)

 

Established SBE Goal: 5.00%

Committed SBE Goal: 6.40%

Fuller & Co. Construction, LLC exceeded the established subcontracting goal and has committed 6.40% ($86,534) of the total contract amount to the following certified firm (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     JT Wilson Hardscapes & Concrete Finishing (SBE) ($36,034) (silt fence, concrete, fence)

§                     Martin Landscaping Co., Inc. (MBE, SBE) ($23,000) (seeding and mulching)

§                     The Survey Company, Inc. (SBE) ($15,000) (surveying)

§                     Pipe Pros, LLC (SBE) ($12,500) (closed-circuit television, pipe cleaning)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan and Private Developer Contributions

 

Attachments

Attachment(s)

Map