Title
Queens Road West Water Main Replacement Construction
Action
Action:
Approve a contract in the amount of $3,351,028.78 to the lowest responsive bidder Propst Construction Company for the Queens Road West Water Main Replacement Project.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
Jackie Jarrell, Charlotte Water
Scott Clark, Charlotte Water
Explanation
* This contract will install 4,300 linear feet of 8-inch water main along East Boulevard between Maryland Avenue and Queens Road and Queens Road West between East Boulevard and Selwyn Avenue (Council District 6).
* This project will replace the existing water main along East Boulevard and Queens Road West, which has reached the end of its useful life.
* On February 24, 2022, the City issued an Invitation to Bid; three bids were received.
* Propst Construction Company was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by first quarter 2023.
Charlotte Business INClusion
Established MBE Goal: 3.00%
Committed MBE Goal: 3.00%
Propst Construction Company met the established MBE subcontracting goal and has committed $100,531 or approximately 3.00% of the total contract amount to the following certified firm (Part B: Section 3 of the Charlotte Business INClusion Policy):
* Silverback Brothers, LLC (MBE, SBE) ($100,531) (hauling)
Established SBE Goal: 8.00%
Committed SBE Goal: 8.00%
Propst Construction Company met the established SBE subcontracting goal and has committed $268,082 or approximately 8.00% of the total contract amount to the following certified firm (Part B: Section 3 of the Charlotte Business INClusion Policy):
* Trull Contracting, LLC (WBE, SBE) ($214,647) (paving, resurfacing street, construction sidewalk and driveway)
* Mohawk Traffic Services, Inc. (SBE) ($41,960) (traffic control services)
* Soggy Bottom Erosion Control, LLC (SBE) ($11,475) (erosion control services, fence installation)
Fiscal Note
Funding: Charlotte Wa...