File #: 15-17451    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 2/18/2022 In control: City Council Business Meeting
On agenda: 3/28/2022 Final action: 3/28/2022
Title: Design Northwest Division Police Station
Attachments: 1. Map_Design Northwest Division Police Station.pdf
Title
Design Northwest Division Police Station

Action
Action:
Approve a contract in the amount of $1,257,403 with Southside Constructors, Inc. for Phase 1 Services of the CMPD Northwest Division Progressive Design-Build Project.

Body
Staff Resource(s):
Phil Reiger, General Services
Craig Fox, General Services
Kathleen Cishek, General Services

Explanation
* This project includes design of a 14,000-square-foot facility with approximately 120 parking spaces on the combined parcels of 1800 and 1818 Mt Holly-Huntersville Road in Council District 2.
* The rezoning request was approved by City Council on February 21, 2022, and this facility will be the last of six completed as per Charlotte-Mecklenburg Police Department's 2015 Masterplan.
* On August 10, 2020, the City issued a Request for Qualifications (RFQ); 11 responses were received.
* Southside Constructors, Inc. is the best qualified firm to meet the City's needs on the basis of demonstrated competence and qualification of professional services in response to the RFQ requirements.
* Progressive Design-Build consists of two-phases. Phase 1 delivers the project up to 100 percent design and Phase 2 will provide a guaranteed maximum price to construct the project. Council will be asked to approve a future amendment for Phase 2.
* The City's design-build delivery method is in conformance with NC General Statute Section 143-128.1(a) and consistent with the Design-Build Institute of America best practices.

Charlotte Business INClusion
The City negotiates participation for Design-Build contracts after the firm is selected and scopes of work are defined for design and construction services (Part G: Section 2.4 of the Charlotte Business INClusion Policy) Southside Constructors, Inc. has committed 12.82% or approximately $161,200 of the total contract for design and construction administrative services to the following firm(s):
? AME Consulting Engineers, PC (SBE) ($141,000) (engineering)
? CS Plumbing Inc. (M...