Title
Roadway Construction Services
Action
Action:
A. Approve a contract in the amount of $1,896,323 to the lowest responsive bidder Blythe Development Co. for the Specialized Roadway Construction Services FY22-C project, and
B. Approve a contract in the amount of $1,891,095.25 to the lowest responsive bidder United of Carolinas, Inc. for the Specialized Roadway Construction Services FY22-D project.
Body
Staff Resource(s):
Phil Reiger, General Services
Jennifer Smith, General Services
Veronica Wallace, General Services
Explanation
* These contracts will be used to construct various transportation infrastructure projects throughout the City.
* Work includes concrete sidewalk and accessible ramps, milling, asphalt paving, and pavement markings.
* Approximately eight projects may be constructed within the contract term of 24 months for each contract. The number of projects may vary depending on the nature and extent of the construction.
Action A
* On July 28, 2021, the City issued an Invitation to Bid; three bids were received.
* Blythe Development Co. was selected as the lowest responsive, responsible bidder.
Action B
* On July 29, 2021, the City issued an Invitation to Bid; three bids were received.
* United of Carolinas, Inc. was selected as the lowest responsive, responsible bidder.
Charlotte Business INClusion
Action A
Established MBE Goal: 8.00%
Committed MBE Goal: 8.00%
Blythe Development Co. has identified MBEs on its project team, and for each work order issued, committed 8.00% of the total contract amount to the following certified firms:
* Diamond Trucking of NC Inc (MBE, SBE) (hauling)
* R.R.C. Concrete, Inc (MBE, SBE) (curb and gutter)
Established SBE Goal: 18.00%
Committed SBE Goal: 18.00%
Blythe Development Co. has identified SBEs on its project team, and for each work order issued, committed 18.00% of the total contract amount to the following certified firms:
* On Time Construction, Inc. (WBE, SBE) (masonry)
* Pentacle Inc. (WBE...