City of Charlotte Banner
File #: 15-15598    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 4/12/2021 In control: City Council Business Meeting
On agenda: 6/28/2021 Final action: 6/28/2021
Title: Airport Passenger Boarding Bridges and Ground Support Equipment Installation and Commissioning

Title

Airport Passenger Boarding Bridges and Ground Support Equipment Installation and Commissioning

 

Action

Action:

A.                     Approve a unit price contract with AERO BridgeWorks, Inc. for the installation and commissioning of Passenger Boarding Bridges, ground support equipment, and spare parts for an initial term of three years, and

 

B.                     Authorize the City Manager to renew the contract for up to two, one-year terms with possible price adjustments and to amend the contract consistent with the purpose for which the contract was approved.

 

Body

Staff Resource(s):

Haley Gentry, Aviation

Jack Christine, Aviation

 

Explanation

§                     This contract provides for the procurement, installation, and commissioning of Passenger Boarding Bridges (PBB), associated ground support equipment, and spare parts. 

§                     The Airport will add 17 PBBs to Concourse E to improve safety and security by restricting access to the ramp. The new PBBs will also provide a better passenger experience by protecting passengers from the elements during boarding and deplaning operations.

§                     This contract will also replace 19 PBBs on other concourses that have reached the end of their useful service life.

§                     On February 11, 2021, the city issued a Request for Proposals (RFP); one response was received.

§                     AERO BridgeWorks, Inc. meets the city’s needs in terms of qualifications, experience, cost, and responsiveness to RFP requirements.

§                     Annual expenditures are estimated to be $8,100,000.

§                     This activity is occurring on Airport property located in Council District 3.

 

Charlotte Business INClusion

The city negotiates subcontracting participation after the proposal selection process (Part C: Section 2.1(h) of the Charlotte Business INClusion Policy). Aero BridgeWorks, Inc. has identified the following certified firm to be utilized as the project evolves:

§                     Besco Electric Corporation (MBE) (electrical) 

 