Title
Upper Taggart Creek Outfall Replacement Change Order
Action
Action:
Approve change order #1 for $2,598,720 to Park Construction of North Carolina, Inc. for Upper Taggart Creek Outfall Replacement project.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Carl Wilson, Charlotte Water
Explanation
§ This project includes the replacement of approximately 10,000 linear feet of sanitary sewer ranging in sizes from eight-inch to 36-inch serving the customers located near Billy Graham Parkway and West Boulevard (Council District 3). This project will include a deep excavation (40 to 50 feet deep) and tunneling methods to install a 36-inch sanitary sewer.
§ This change order is needed due to exceeding the anticipated rock quantities. Originally, 13,000 cubic yards of rock was estimated. This was exceeded by approximately 16,000 cubic yards.
§ On February 24, 2020, City Council approved a contract with Park Construction of North Carolina, Inc. for construction of the Upper Taggart Creek Outfall Replacement project.
§ The unit price for cubic yard of rock provided by the contractor will not change for the overage.
§ The new total value of the contract is $19,365,585.36.
Charlotte Business INClusion
All additional work involved in this Change Order will be performed by Park Construction of North Carolina, Inc. and their existing subcontractors (Part D: Section 6 of the Charlotte Business INClusion Policy).
Fiscal Note
Funding: Charlotte Water Capital Investment Plan
Attachments
Attachment(s)
Map