Title: Construct Starvalley 7141 Storm Drainage Improvement Project
Attachments: 1. Map_Construct Starvalley 7141 Storm Drainage Improvement Project
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.
Title
Construct Starvalley 7141 Storm Drainage Improvement Project

Action
Action:
Approve a contract in the amount of $2,159,565.60 to the lowest responsive bidder United Construction Company, Inc for the Starvalley 7141 Storm Drainage Improvement project.

Body
Staff Resource(s):
Angela Charles, Charlotte Water
Mike Davis, Storm Water Services
Matt Gustis, Storm Water Services

Explanation
* This project will improve deteriorating pipe in the roadway and reduce flooding of properties and structures in the lower Little Sugar Creek watershed with boundaries of Starmount Cove Lane to the north, Mapleridge Drive to the south, Thorncliff Drive to the east, and South Boulevard to the west, in Council District 6.
* Construction will include the installation of storm drainage, drainage system rehabilitation, water/sanitary sewer, curb, gutter, and driveways.
* On January 8, 2021, the city issued an Invitation to Bid; three bids were received.
* United Construction Company, Inc was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by third quarter 2022.

Charlotte Business INClusion
Established MBE Goal: 7.00%
Committed MBE Goal: 7.04%
United Construction Company, Inc exceeded the established MBE subcontracting goal and has committed 7.04% ($152,000) of the total contract amount to the following MBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):
??R.R.C. Concrete Inc (MBE, SBE) ($110,000) (concrete)
??Streeter Trucking Company, Inc. (MBE, SBE) ($42,000) (hauling)

Established SBE Goal: 19.00%
Committed SBE Goal: 19.22%
United Construction Company, Inc exceeded the established SBE subcontracting goal and has committed 19.22% ($415,000) of the total contract amount to the following SBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):
??Carolina Cajun (SBE) ($195,000) (grading/piping)
??Countywide Commercial (SBE) ($120,000) (asphalt/paving)
??AMP U...