File #: 15-14586    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 11/4/2020 In control: City Council Business Meeting
On agenda: 12/14/2020 Final action:
Title: Construct Alleghany Street Pedestrian/Bicycle Improvements
Attachments: 1. Map_Construct Alleghany Street Pedestrian-Bicycle Improvements.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Construct Alleghany Street Pedestrian/Bicycle Improvements

 

Action

Action                     

Approve a contract in the amount of $831,821.76 to the lowest responsive bidder Armen Construction, LLC for the Alleghany Pedestrian/Bicycle Improvements project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Jennifer Smith, General Services

 

Explanation

§                     This project will include the construction of approximately 1.2 miles of sidewalk on the north side of Alleghany Street from Wilkinson Boulevard to Ashley Road in Council District 3. 

§                     Work includes sidewalk, curb and gutter, pedestrian refuge islands, new curb ramps, milling, resurfacing, and restriping.

§                     Bicycle lanes will also be included along Alleghany Street as part of the project. 

§                     On October 6, 2020, the city issued an Invitation to Bid; four bids were received. Armen Construction bid $831,821.76 with an 8.0% MBE Goal. Carolina Cajun Concrete, Inc. bid $929,959.80 with an 8.1% MBE Goal. Little Mountain Builders of Catawba, Inc. bid $937,072.12 with an 9.9% MBE Goal. United Construction Company, Inc. bid $982,466.10 with an 8.04% MBE Goal.

§                     Armen Construction, LLC was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by fourth quarter 2021.

 

Charlotte Business INClusion

Armen Construction, LLC is a city certified MBE and SBE.

 

Established MBE Goal: 8.00%

Committed MBE Goal: 8.00%

Armen Construction, LLC met the established MBE subcontracting goal, and has committed 8.00% ($66,585) of the total contract amount to the following MBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     B & M Concrete, Inc. (MBE, SBE) ($36,955) (concrete)

§                     Cesar A Leon L.L.C. (MBE, SBE) ($17,000) (hauling)

§                     Mid-Atlantic Erosion Control, Inc. (MBE, SBE) ($12,630) (erosion control)

 

Fiscal Note

Funding:  General Capital Investment Plan

 

Attachments

Attachment(s)

Map