Title

Construct Collective Storm Drainage Improvement Projects Series G

 

Action

Action                     

Approve a contract in the amount of $1,639,877.14 to the lowest responsive bidder OnSite Development, LLC for the Collective Storm Drainage Improvement Projects Series G project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Mike Davis, Storm Water Services

Matt Gustis, Storm Water Services

 

Explanation

§                     This contract is part of an ongoing program to provide repairs and/or improvements to storm drainage systems.

§                     This contract will address failing storm drainage systems in the following locations:

-                     300 Hampton Church Road (Council District 4),

-                     2046 Lynwood Drive (Council Districts 1 and 6),

-                     1357 Sharon Road West (Council District 6), and

-                     10109 Zackery Avenue (Council District 7).

§                     Work includes grading, drainage, sidewalks, and curb and gutter.

§                     On October 20, 2020, the city issued an Invitation to Bid; five bids were received.

§                     OnSite Development, LLC was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by first quarter 2022.

 

Charlotte Business INClusion

Established MBE Goal: 8.00%

Committed MBE Goal: 10.32%

Onsite Development, LLC met the established MBE subcontracting goal and has committed 10.32% ($169,230) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     R.R.C. Concrete Inc (MBE, SBE) ($75,000) (concrete)

§                     MTS Trucking Inc. (MBE, SBE) ($47,115) (hauling)

§                     Streeter Trucking Company, Inc. (MBE, SBE) ($47,115) (hauling)

 

Established SBE Goal: 21.00%

Committed SBE Goal: 21.01%

Onsite Development, LLC met the established SBE subcontracting goal and has committed 21.01% ($344,460) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     AMP Utility Distribution Services, LLC (WBE, SBE) ($76,000) (materials)

§                     LJR Concrete LLC (SBE) ($80,000) (concrete)

§                     Affordable Source Trucking, LLC (MBE, SBE) ($47,115) (hauling)

§                     RAH Trucking Inc. (MBE, SBE) ($47,115) (hauling)

§                     Solanos Trucking Company, Inc. (SBE) ($47,115) (hauling)

§                     Tony’s Trucking Inc.  (MBE, SBE) ($47,115) (hauling)

 

Fiscal Note

Funding:  Storm Water Capital Investment Plan

 

Attachments