Title: Construct Country Club Drive Storm Drainage Improvement Project
Attachments: 1. Map_Construct Country Club Drive Storm Drainage Improvement Project.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Construct Country Club Drive Storm Drainage Improvement Project

 

Action

Action:                       

A.                     Reject the low-bid submitted by Nassiri Development, LLC for the Country Club Storm Drainage Improvement project, and

 

B.                     Approve a contract in the amount of $998,328.80 to the lowest responsive, responsible bidder Husky Construction Corp. for the Country Club Storm Drainage Improvement project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Mike Davis, Storm Water Services

Matt Gustis, Storm Water Services

 

Explanation

§                     This project is located in the Briar Creek watershed in the 3000 block of Country Club Drive with boundaries of Shamrock Gardens Elementary School to the north, Charlotte Country Club to the south, Anne Street to the east, and Stoneybrook Road to the west, in Council District 1. 

§                     This project will reduce roadway flooding and support upstream drainage improvements.

§                     This contract will improve approximately 370 linear feet of storm drainage pipe and associated sanitary sewer, water lines, sidewalk, curb, gutter, and paving.

§                     On June 18, 2020, the city issued an Invitation to Bid; 11 bids were received.

§                     The low-bid submitted by Nassiri Development, LLC did not meet the criteria to be deemed responsible for this project.

§                     Husky Construction Corp. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by third quarter 2021.

 

Charlotte Business INClusion

Husky Construction Corp. is a city certified SBE.

 

Established MBE Goal: 7.00%

Committed MBE Goal: 7.01%

Husky Construction Corp. met the established MBE subcontracting goal and has committed 7.01% ($70,000) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     R.R.C. Concrete Inc (MBE, SBE) ($25,000) (abutment work, concrete)

§                     Streeter Trucking Company, Inc. (MBE, SBE) ($45,000) (hauling)

 

Established SBE Goal: 18.00%

Committed SBE Goal: 22.59%

Husky Construction Corp. exceeded the established SBE subcontracting goal and has committed 22.59% ($225,500) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     AMP Utility Distribution Services, LLC (WBE, SBE) ($180,000) (utility supplies)

§                     Maybury Fencing Inc. (WBE, SBE) ($23,000) (fencing)

§                     Ram Pavement Services, Inc. (SBE) ($15,000) (asphalt, milling, thermo)

§                     Mor Construction, LLC (SBE) ($7,500) (demo, curb & sidewalk)

 

Fiscal Note

Funding: Storm Water Capital Investment Plan

 