Title: Construct Margaret Wallace Road Sidewalk
Attachments: 1. Map_Construct Margaret Wallace Road Sidewalk.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Construct Margaret Wallace Road Sidewalk

 

Action

Action                     

Approve a contract in the amount of $981,975.50 to the lowest responsive bidder Husky Construction Corp. for the Margaret Wallace Road (Campbell Creek - Old Gate Drive) Sidewalk project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Jennifer Smith, General Services

Allison Brickey, General Services

 

Explanation

§                     This project will construct approximately 0.5 miles of new sidewalk along the south side of Margaret Wallace Road from Campbell Creek to Old Gate Drive in Council District 5.

§                     Work includes the construction of sidewalk, curb and gutter, driveways, pedestrian refuge island, retaining walls, pedestrian bridge, asphalt paving, and storm drainage.

§                     On July 1, 2020, the city issued an Invitation to Bid; five bids were received.

§                     Husky Construction Corp. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by second quarter 2021.

 

Charlotte Business INClusion

Husky Construction Corp. is a certified SBE.

 

Established MBE Goal: 7.00%

Committed MBE Goal: 7.03%

MBE Participation to Date:7.03%

Husky Construction Corp. exceeded the established MBE subcontracting goal, and has committed 7.03% ($69,000) of the total contract amount to the following MBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     R.R.C. Concrete Inc. (MBE, SBE) ($69,000) (forming, pouring)

 

Established SBE Goal: 17.00%

Committed SBE Goal: 4.94%

SBE Participation to Date: 21.97%

Husky Construction Corp. failed to meet the established subcontracting goal, but has earned the required Good Faith Efforts (Part C: Section 5 of the Charlotte Business INClusion Policy). Husky Construction Corp. has committed 4.94% ($48,500) of the total contract amount to the following SBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Streeter Trucking Company, Inc. (MBE, SBE) ($25,000) (hauling)

§                     Ram Pavement Services, Inc. (SBE) ($10,000) (asphalt, materials, milling)

§                     Cochrane Steel, Inc. (SBE) ($8,500) (rebar)

§                     AMP Utility Distribution Services, LLC (SBE) ($5,000) (material)

 

Subsequent to Bid Opening, Husky Construction Corp. has committed an additional 17.03% ($167,225) of the total contract amount to the following SBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Streeter Trucking Company, Inc. (MBE, SBE) ($40,000) (hauling)

§                     Maybury Fencing Inc. (SBE) ($38,000) (safety rail)

§                     R.R.C. Concrete Inc. (MBE, SBE) ($19,000) (curb & gutter, abutments)

§                     Ram Pavement Services, Inc. (SBE) ($18,000) (asphalt, materials, milling, thermo)

§                     Cochrane Steel, Inc. (SBE) ($16,100) (rebar)

§                     GDC, Inc. (MBE, SBE) ($5,300) (traffic control)

§                     Lopez Rebar LLC (SBE) ($10,200) (tie rebar)

§                     Mor Construction, LLC (SBE) ($13,125) (modular retaining wall)

§                     AMP Utility Distribution Services, LLC (SBE) ($7,500) (material)

 

Fiscal Note

Funding:  General Capital Investment Plan

 

Attachments

Attachment(s)

Map