Beaverdam Trunk Sanitary Sewer Construction
Action
Action:
A. Approve a contract in the amount of $2,382,209.54 to the lowest responsive bidder Dellinger Inc. for the Beaverdam Trunk Sanitary Sewer project,
B. Approve an amendment to the five-year developer reimbursable contract with Crescent Dixie River, LLC modifying the estimated cost to $3,070,000, and
C. Adopt a budget ordinance appropriating $2,800,000 from Crescent Dixie River, LLC.
Body
Staff Resource(s):
David Czerr, Charlotte Water
Ron Hargrove, Charlotte Water
Carl Wilson, Charlotte Water
Explanation
Action A
§ This contract will install approximately 7,000 linear feet of 24-inch sanitary sewer off Dixie River Road in the River District adjacent to Council District 3.
§ On June 23, 2020, the city issued an Invitation to Bid; nine bids were received.
§ Dellinger Inc. was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by second quarter 2021.
Actions B and C
§ On March 26, 2018, Council approved a five-year reimbursable contract with Crescent Dixie River, LLC and a budget ordinance appropriating $270,000 for the design phase of the project.
§ The amendment will increase the amount of the agreement to include construction, inspection services, project administration, and any other expenses accrued from construction for a total estimated cost of $3,070,000.
§ The budget ordinance will increase the amount of the project budget to coincide with the agreement less deposits received.
Charlotte Business INClusion
Action A
Established MSBE Goal: 7.00%
Committed MSBE Goal: 8.37%
MSBE Participation to Date: 8.80%
Dellinger Inc. met the established subcontracting goal and has committed $199,481 or approximately 8.37% of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
§ Mid Atlantic Erosion Control, Inc. (MBE, SBE) ($87,404) (silt fence and stone installation)
§ Sanders Constructors (SBE) ($74,000) (right of way clearing and grubbing)
§ All Points Trucking, Inc. (WBE, SBE) ($38,077) (hauling)
Dellinger Inc. continues to work towards increasing their participation and, subsequent to the Bid Opening, has committed an additional $10,200 or approximately 0.43% to the following certified firm:
§ Soggy Bottom Erosion Control, LLC (SBE) ($10,200) (seed and straw right of way)
Fiscal Note
Funding: Charlotte Water Capital Investment Plan
Attachments
Attachment(s)
Map