Title
Construct Oneida Road Sidewalk and Culvert Replacement Project
Action
Action:
Approve a contract in the amount of $1,372,112.53 to the lowest responsive bidder NJR Group, Inc. for the Oneida Road Sidewalk and Culvert Replacement project.
Body
Staff Resource(s):
Phil Reiger, General Services
Veronica Wallace, General Services
Matt Gustis, General Services
Explanation
§ This project will install concrete sidewalk and accessible curb ramps along Oneida Road from Graham Street to Garvis Drive in Council District 4.
§ The project will also include the replacement of a storm drainage culvert near the intersection of Oneida Road and Osage Circle.
§ On May 11, 2020, the city issued an Invitation to Bid; 10 bids were received.
§ NJR Group, Inc. was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by third quarter 2021.
Charlotte Business INClusion
Established MBE Goal: 7.00%
Committed MBE Goal: 12.21%
NJR Group, Inc. exceeded the established MBE subcontracting goal and has committed 12.21% ($167,509) of the total contract amount to the following MBE certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
§ R.R.C. Concrete Inc (MBE, SBE) ($134,794) (concrete)
§ Martin Landscaping Co. (MBE, SBE) ($32,715) (erosion control)
Established SBE Goal: 19.00%
Committed SBE Goal: 26.07%
NJR Group, Inc. exceeded the established SBE subcontracting goal and has committed 26.07% ($357,665) of the total contract amount to the following SBE certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
§ B&N Grading, Inc. (SBE) ($188,381) (asphalt, utilities)
§ R.R.C. Concrete Inc (MBE, SBE) ($134,794) (concrete)
§ Martin Landscaping Co. (MBE, SBE) ($32,715) (erosion control)
§ Ground Effects, Inc. (SBE) ($1,775) (thermo)
Fiscal Note
Funding: Transportation Capital Investment Plan and Storm Water Capital Investment Plan