City of Charlotte Banner
File #: 15-12843    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 2/10/2020 In control: City Council Business Meeting
On agenda: 3/16/2020 Final action:
Title: Mount Holly Pump Station and Force Main Construction
Attachments: 1. Map-Mount Holly Pump Station and Force Main Construction
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Mount Holly Pump Station and Force Main Construction

 

Action

Action:

Approve a guaranteed maximum price of $829,219 to The Haskell Company for the purchase of materials and equipment needed for Design-Build construction services for the Mount Holly Pump Station and Force Main project.

 

Body

Staff Resource(s):

David Czerr, Charlotte Water

Ron Hargrove, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

                     The Haskell Company has developed a guaranteed maximum price (GMP) for the purchase of specialized materials and equipment required for construction of improvements at existing facilities.

                     This project will design and construct pump stations and pipelines and modify existing infrastructure that will enable the City of Mount Holly to send its sanitary sewer flow into the future Stowe Regional Water Resource Recovery Facility (adjacent to Council Districts 2 and 3).

                     The city and Mount Holly have agreed to construct this project through resolutions and agreements with Mount Holly and Gaston County approved by Council on September 10, 2018 and December 11, 2018. 

                     On July 8, 2019, Council approved a contract with The Haskell Company for Design-Build design services.

                     Council will receive future requests for the approval of remaining project GMPs once the GMPs are established.

 

Charlotte Business INClusion

This project is subject to the North Carolina Clean Water State Revolving Fund (CWSRF) loan program guidelines. There are no MWBEs certified to perform the scopes of work that the city regards as realistic opportunities for subcontracting.

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 