City of Charlotte Banner
File #: 15-9388    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 10/8/2018 In control: City Council Business Meeting
On agenda: 11/26/2018 Final action: 11/26/2018
Title: Fire Station 26 Mechanical Systems Upgrades
Attachments: 1. Location Map - Fire Station 26 Mechanical Systems Upgrades

Title

Fire Station 26 Mechanical Systems Upgrades

 

Action

Action:

Approve a contract in the amount of $122,478 to the lowest responsive bidder Armstrong Mechanical Services, Inc. for the Fire Station 26 Mechanical Systems Upgrades project.

 

Body

Staff Resource(s):

Mike Davis, Engineering and Property Management

William Haas, Engineering and Property Management

Reginald Johnson, Fire

Kevin Gordon, Fire

 

Explanation

§                     The project involves the replacement of the HVAC equipment at Fire Station 26, located at 9231 South Tryon Street (Council District 3).

§                     The equipment has reached the end of its useful life and is in need of replacement.

§                     The work will include:

-                     Removal of existing HVAC equipment,

-                     Replacement of two existing split system furnaces with two new split system furnaces and one split system heat pump,

-                     Replacement of two electric wall heaters with two mini-split systems, and

-                     Upgraded control system.

§                     On October 9, 2018, the City issued an Invitation to Bid; one bid was received.

§                     Armstrong Mechanical Company, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by first quarter 2019.

 

Charlotte Business INClusion

The City solicited bids only from City-certified SBEs, therefore 100% of the project participation is being committed to the following certified firm: Armstrong Mechanical Services, Inc. (SBE) (Part A: Section 2.3 of the Charlotte Business INClusion Policy). Armstrong Mechanical Services, Inc. (SBE) has committed 13.68% ($16,750) of the total contract amount to the following certified firms:

§                     Controls Service Group (SBE) ($9,250) (Building Controls)

§                     Electric System Specialists, Inc. (SBE) ($7,500) (Electrical)

 

Fiscal Note

Funding: General Community Investment Plan

 

Attachments

Attachment(s)

Map